Skip to main content

CAG Picks Holes In LCA Project, Says It Fails To Meet IAF Requirements

India's Tejas Light Combat Aircraft project, in the works for over three decades, came under severe criticism from CAG today as it pointed out that its Mark-I version has 53 "significant shortfalls" which have reduced its operational capabilities as well as survivability.

Not only that, IAF would be "constrained" to induct the fighter LCA without availability of a trainer model, thereby "adversely impacting pilot training", the audit body said in a report tabled in Parliament.


The CAG noted that it was due to the delay in the manufacture and supply of LCA that IAF had to go for alternative temporary measures such as upgrading its MIG BIS, MiG-29, Jaguar, and Mirage aircraft at a cost of Rs 20,037 crore and revise the phasing out of MiG-21s.


LCA
LCA

"LCA Mark-I, which achieved Initial Operational Clearance (December, 2013) has significant shortfalls (53 permanent waivers/concessions" in meeting ASR (Air Staff Requirements) as a result of which it will have reduced operational capabilities and reduced survivability, thereby limiting its operational employability when inducted into IAF squadrons," the report said.


Listing the shortcomings, the CAG said that the LCA Mark- I fails to meet the electronic warfare capabilities sought by IAF as the Self-Protection Jammer could not be fitted on the aircraft due to space constraints.


Also, it said that the Radar Warning Receiver/Counter Measure Dispensing System fitted on the aircraft had raised performance concerns which are yet to be overcome till January this year.


It added that the shortcomings in the Mark-I (increased weight, reduced internal fuel capacity, non-compliance of fuel system protection, pilot protection from front, reduced speed) are expected to be overcome in the Mark-II model.


"LCA Mark-I does not meet the ASR. The deficiencies are now expected to be met in LCA Mark-II by December 2018," the CAG said.





While DRDO has always showcased LCA, christened Tejas, as an indigenously-developed aircraft and the indigenous content of the LCA was estimated by ADA to be 70 per cent, the CAG said it "actually worked out to about 35 per cent" as of January this year.

Systems such as Kaveri engine, Multi-Mode Radar, Radome, Multi-Functional Display System and Flight Control System Actuators taken up for indigenous development could not be developed successfully, resulting in LCA's continued dependence on the import of these systems, CAG said.


IAF had proposed in the early 1980s that a new aircraft be developed to replace the MiG-21 fleet, manufactured during 1966 and 1987, after its phasing out in the 1990s.


The project for indigenous design and development of LCA was sanctioned in 1983 at a cost of Rs 560 crore, which was enhanced from time to time up to Rs 10,397.11 crore.


The government in June, 1984, constituted an Aeronautical Development Agency (ADA) as a dedicated institution for the management of the LCA project.

IAF had issued Air Staff Requirement (ASR) in October, 1985, envisaging a light-weight multi-mission fighter with contemporary air combat and offensive air support capabilities and excellent manoeuvrability for close air combat at low and medium altitudes.

The projected requirement was for 220 Light Combat Aircraft (200 Fighters, 20 trainers) to be inducted by 1994.


However, LCA could only achieve Initial Operational Clearance in December, 2013, as against the earlier scheduled date of December, 2005.


The Full Operational Clearance (FOC), which was scheduled to be completed by December, 2008, is now slated to be achieved by December this year although experts said even that could be delayed.


The CAG said that ADA's decision to advance the building of two prototypes from Full-Scale Engineering Development (FSED) Phase-II to FSED Phase-I so as to utilise its savings on the grounds of accelerating the development process of LCA had failed to yield the desired results.


This, the report said, was because preponed prototypes were deficient in terms of critical onboard systems (Multi- Mode Radar, Self-Protection Jammer, Radar Warning Receiver) and led to ADA using the Limited Series Production (LSP) aircraft (meant for IAF use) towards flight testing/evaluation of these critical on board systems.


"This was in contravention of the Cabinet approval (November, 2001) for phased development of the prototypes in FSED Phase-II after Technical Demonstrators had been built and flight tested for 210 hours," CAG said.


Talking about lack of trainer aircraft, the audit body said that IAF was in the interim using an upgraded Full Mission Simulator (FMS) at ADA for pilot training, pending supply of an FMS by HAL at the LCA operating base.


It said that the long gestation period led to a change of weapon systems on LCA, necessitating the acquisition of new ones.


The audit body also had a word of appreciation for the ADA, saying its work centres on the indigenous development of the LCA, "which is comparable to many contemporary aircraft in the world".


CAG said that the manufacturing facilities at HAL cater presently to the production of only four aircraft per annum as against the envisaged requirement of eight due to delays in procuring plant and machinery, tools and also construction of production hangars, which would further impact production of LCA and induction into IAF squadrons.


Repair and Overhaul (ROH) facility for LCA, as specified in the ASR, has not been created fully at HAL, the CAG said.


Of the 344 Line Replaceable Units of LCA, 90 LRUs were considered non-repairable, it said. Of the remaining 254 LRUs, while ROH facilities in respect of 185 were available, the same was yet to be established for 69 LRUs as of January this year, the report added.


The CAG stressed on the need for more efficient management of planning and execution of aircraft development programmes, closer interaction and coordinated efforts among all the stakeholders involved.

It recommended that realistic timelines should be set by MoD while seeking approval for such projects from the government and that the same should be adhered to during their execution with coordinated planning and an effective in-built monitoring mechanism.

"In view of the complexity of the technology involved, while deviating from the approved plan of development, ADA should consult the user (Air HQ) and obtain prior approval of sanctioning authority/ministry for such deviations so as to minimise waivers and concessions at the time of acceptance by the user (IAF)," it said.


The agencies -- DRDO, ADA and HAL -- should undertake the projects strictly in conformity with the specifications projected by IAF, who should be involved right from the planning stage so as to ensure timely achievement of their requirements.


Indigenisation efforts should be made in coordination with all the agencies involved by having a well-defined indigenisation plan and a clear roadmap for developing a quality product as per the requirement so as to avoid import substitution, it said.


"MoD should award contract to production agency at an appropriate stage of development of a system/equipment in order to avoid the necessity of extending delivery schedule due to a delay in the development of the system, apart from the resultant blocking of funds/inventory and to overcome obsolescence of the components procured by the production agency," the CAG said.

Comments

Popular posts from this blog

Pakistani JF-17 A Thunder OR A Blunder

Pakistan has witnessed new defense acquisitions in this decade than any other, and in the center of it all is the new fighter which was designed by China with partial funding from Pakistan. It is formally known as JF-17 Thunder. When the fighter was in development, Pakistani online communities were jumping with excitement comparing it with its arch rival India’s modern combatants Su-30MKI, Mig-29S & Mirage-2000H. There were claims of it featuring western Radars and long range missiles, & Chinese ordering some due to its superior capabilities. But the reality is far from it. China having spent significant amount of money into a fighter which it is never going to use, most probably forced Pakistan to accept its avionics to offset some its development costs. Chinese who are known for their self reliance first and quality next, are further downgrading JF-17s capabilities with their poorly copy-pirated avionics. Along with their dubious weapons, any chance of JF...

India Planned Attack On Pak Navy Mehran Base To Kill Chinese Engineers

The terrorist attack on Karachi's Mehran Naval Station on May 22 was conceived and launched by India with the primary objective of killing the Chinese engineers present there, a Pakistani newspaper has claimed, citing 'informed sources'. Four to six Taliban terrorists had entered PNS Mehran on May 22, destroying two maritime surveillance aircraft and killing ten military personnel during their 17-hour siege of the naval air base. "India is the only country in the region that feels troubled by the Pakistan Navy, which had awfully beaten the Indian Navy in Operation Dwarka of 1965. Since then, it has been an earnest desire of India to harm the Pakistan Navy but it was perhaps not possible on the battle front, hence it struck the PNS Mehran," The News quoted sources as saying.

Pakistani F-16s Shoot Down RAF Eurofighter Typhoons During Air Combat Exercises In Turkey

Pakistani pilots flying modernised versions of the 1970s-vintage F-16 Falcon fighter have beaten the RAF's brand-new Eurofighter Typhoon superfighters during air combat exercises in Turkey, according to a Pakistani officer. Analysis: The RAF Typhoon, formerly known as the Eurofighter, should nonetheless have been vastly superior in air-to-air combat whether BVR or close in within visual range (WVR). The cripplingly expensive, long-delayed Eurofighter was specifically designed to address the defects of its predecessor the Tornado F3 – famously almost useless in close-in, dogfighting-style air combat. The Typhoon was meant to see off such deadly in-close threats as Soviet "Fulcrums" and "Flankers" using short-range missiles fired using helmet-mounted sight systems: such planes were thought well able to beat not just Tornados but F-16s in close fighting, and this expectation was borne out after the Cold War when the Luftwaffe inherite...